Wastewater Treatment Plant | STP Plant | ETP Plant – Inovar

Smart STP Solution: 40% Space Saved, Installed in Just 4 Days

Package Sewage Treatment Plant (STP) – 200 KLD, Karjat
Client: Hospitality Industry

Inovar’s Solution

Inovar implemented a package STP system using MSFRP tanks, designed as a plug-and-play unit.The system integrated multiple processes aeration, anoxic, settling, filtration, and pumping within a single compact unit.

The treated water, sludge holding, and collection tanks were constructed in civil work, while the MSFRP package unit was mounted above them, minimizing space and installation time.

Outcome

  • Installation completed in just 3–4 days, fully pre-assembled at the factory.
  • 40% space saved compared to conventional civil systems.
  • Easy maintenance due to above-ground design and modular access.
  • Lower operational costs due to efficient process integration.
  • Relocatable system for future expansion or site changes.

Key Benefits

  • Plug-and-play installation with minimal site disruption.
  • Compact footprint up to 40% smaller than civil systems.
  • Pre-tested at the factory, ensuring quick commissioning.
  • Simplified O&M with easy accessibility.
  • Long service life with corrosion-resistant MSFRP construction.

The Challenge

The client’s premises were scattered, requiring a compact, efficient, and easy-to-maintain STP setup. Traditional civil STPs posed several challenges:

Got more questions? Speak to our experts...