Smart STP Solution: 40% Space Saved, Installed in Just 4 Days
A hospitality client in Karjat needed a compact, maintainable STP. A pre-assembled MSFRP package unit replaced conventional civil works — installed in 3–4 days.
8 case studies

A hospitality client in Karjat needed a compact, maintainable STP. A pre-assembled MSFRP package unit replaced conventional civil works — installed in 3–4 days.

Sludge at 65% moisture, 15–20 days of open-air drying and a batch filter press — replaced with continuous drying to 5% moisture. ROI inside six months.

An automobile ETP with 50–100 ppm hexavalent chromium and mixed streams. Segregation and internal reagent reuse cut OPEX 70% and stretched membrane cleaning to 8–10 months.

A compact STP that looked fine on paper kept breaching nitrogen limits. The cause was a missing anoxic stage, not failing equipment. How we redesigned it.

DMAC at 200 ppm was killing the biology in a pharma ETP. Segregation plus H₂O₂/UV oxidation took it below 1 ppm at discharge and cut OPEX by around 70%.

A Goa ETP kept failing norms — not because of the water, but because humid-climate sludge drying never kept up. How mechanical dewatering stabilised it.

Membranes were choking every 3–4 days. Rather than sell replacements, we fixed the pre-filtration and water chemistry — membrane life went past a month.

Fluoride at 70 ppm, corroding GI pipelines and a failed removal system. How pre-treatment redesign, not membranes alone, delivered under 1 ppm and 88% recovery.